FRC Build Schedule
FRC Build Schedule
Start: | January 5, 2014 |
Finish: | February 19, 2014 |
Report Date: | January 8, 2014 |
Gantt Chart
WBS | Name | Work |
---|---|---|
1 | Conceptualize | 2d |
1.1 | Strategy | 2d |
1.1.1 | Autonomous | 1d |
1.1.2 | Tele-Op | 1d |
2 | Design | 36d |
2.1 | Chassis | 6d |
2.1.1 | AndyMark | 1d |
2.1.2 | Scaffolding | 5d |
2.2 | Manipulatives | 15d |
2.2.1 | Pinchers | 5d |
2.2.2 | Net/Catch Device | 5d |
2.2.3 | Ramp | 5d |
2.3 | Drive train | 15d |
2.3.1 | Wheels | 5d |
2.3.2 | Motor | 5d |
2.3.3 | Transmission | 5d |
3 | Construction | 75d |
3.1 | Fabrication | 30d |
3.2 | Chassis | 3d |
3.3 | Drive train | 14d |
3.4 | Wiring Board | 3d |
3.5 | field obstacles | 7d |
3.6 | Manipulators | 18d |
3.7 | Stop Build | |
4 | Programming | 76d |
4.1 | Install OS | 3d |
4.2 | cRIO Configuration | 1d |
4.3 | Autonomous System | 36d |
4.4 | Control Systems | 36d |
4.5 | System Test | |
4.6 | Systems Test | |
5 | Drive Team | 15d |
5.1 | Practice/test | 15d |
5.2 | Day 0 @ Central | |
6 | Marketing | 149d |
6.1 | T-shirt | 14d |
6.2 | Student Store | 45d |
6.3 | Fundraising | 45d |
6.4 | Website | 45d |
6.4.1 | Blog | 45d |
7 | Day 0 |
Week 2, 2014 | Week 3, 2014 | Week 4, 2014 | Week 5, 2014 | Week 6, 2014 | Week 7, 2014 | Week 8, 2014 | ||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
Programming, Electrical
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
◆
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
◆
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
◆
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
◆
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
◆
|
Tasks
WBS | Name | Start | Finish | Work | Complete | Cost | Assigned to | Notes |
---|---|---|---|---|---|---|---|---|
1 | Conceptualize | Jan 6 | Jan 6 | 2d | ||||
1.1 | Strategy | Jan 6 | Jan 6 | 2d | Build Team, Programming, Media, Marketing, Electrical, Drive | |||
1.1.1 | Autonomous | Jan 6 | Jan 6 | 1d | 0% | |||
1.1.2 | Tele-Op | Jan 6 | Jan 6 | 1d | 0% | |||
2 | Design | Jan 7 | Jan 15 | 36d | Build Team, Programming, Media, Marketing, Electrical, Drive | Conceptualize robot, determine required parts | ||
2.1 | Chassis | Jan 7 | Jan 15 | 6d | ||||
2.1.1 | AndyMark | Jan 7 | Jan 7 | 1d | 0% | |||
2.1.2 | Scaffolding | Jan 11 | Jan 15 | 5d | 0% | |||
2.2 | Manipulatives | Jan 11 | Jan 15 | 15d | ||||
2.2.1 | Pinchers | Jan 11 | Jan 15 | 5d | 0% | |||
2.2.2 | Net/Catch Device | Jan 11 | Jan 15 | 5d | 0% | |||
2.2.3 | Ramp | Jan 11 | Jan 15 | 5d | 0% | |||
2.3 | Drive train | Jan 11 | Jan 15 | 15d | ||||
2.3.1 | Wheels | Jan 11 | Jan 15 | 5d | 0% | |||
2.3.2 | Motor | Jan 11 | Jan 15 | 5d | 0% | |||
2.3.3 | Transmission | Jan 11 | Jan 15 | 5d | 0% | |||
3 | Construction | Jan 11 | Feb 10 | 75d | Build Team, Electrical, Drive | |||
3.1 | Fabrication | Jan 11 | Feb 9 | 30d | 0% | |||
3.2 | Chassis | Jan 11 | Jan 13 | 3d | 0% | |||
3.3 | Drive train | Jan 11 | Jan 24 | 14d | 0% | |||
3.4 | Wiring Board | Jan 11 | Jan 12 | 3d | 0% | Programming, Electrical | ||
3.5 | field obstacles | Jan 11 | Jan 17 | 7d | 0% | |||
3.6 | Manipulators | Jan 20 | Feb 6 | 18d | 0% | |||
3.7 | Stop Build | Feb 10 | Feb 10 | |||||
4 | Programming | Jan 8 | Feb 18 | 76d | Programming, Electrical | |||
4.1 | Install OS | Jan 8 | Jan 10 | 3d | 0% | Install OS, labview, windriver studio, etc. | ||
4.2 | cRIO Configuration | Jan 12 | Jan 13 | 1d | 0% | |||
4.3 | Autonomous System | Jan 13 | Feb 18 | 36d | 0% | |||
4.4 | Control Systems | Jan 13 | Feb 18 | 36d | 0% | |||
4.5 | System Test | Jan 20 | Jan 20 | |||||
4.6 | Systems Test | Feb 1 | Feb 1 | |||||
5 | Drive Team | Feb 1 | Feb 15 | 15d | Media, Marketing, Drive | |||
5.1 | Practice/test | Feb 1 | Feb 15 | 15d | 0% | |||
5.2 | Day 0 @ Central | Feb 15 | Feb 15 | |||||
6 | Marketing | Jan 6 | Feb 19 | 149d | Media, Marketing | |||
6.1 | T-shirt | Jan 6 | Jan 19 | 14d | 0% | |||
6.2 | Student Store | Jan 6 | Feb 19 | 45d | 0% | |||
6.3 | Fundraising | Jan 6 | Feb 19 | 45d | 0% | |||
6.4 | Website | Jan 6 | Feb 19 | 45d | ||||
6.4.1 | Blog | Jan 6 | Feb 19 | 45d | 0% | |||
7 | Day 0 | Feb 19 | Feb 19 |
Resources
Name | Short name | Type | Group | Cost | |
---|---|---|---|---|---|
Build Team | Work | 0 | |||
Drive | Work | 0 | |||
Electrical | Work | 0 | |||
Marketing | Work | 0 | |||
Media | Work | 0 | |||
Programming | Work | 0 |